Planning for wind farm at Bilboa, Carlow
Stock image of a wind turbine on a mountain in Ireland
A PLANNING application for a 195-acre wind farm near the Carlow-Laois border has been submitted to Carlow Co Council and Laois Co Council.
The development, known as the Bilboa Wind Farm, would involve the construction of five wind turbines in the townlands of Clogrennane, Ballinabranna, Craanlusky, Tomard Lower, Tomard Upper, Boolyrathornan, Boolyvannanan and Coolnakisha. The proposed site covers 79 hectares (195 acres).
The new application was submitted on 30 October by Boolyvannanan Renewable Energy Ltd, whose registered address is at Lissarda Business Park, Lissarda, Co Cork. It replaces earlier applications approved by Laois Co Council and Carlow Co Council in 2022, with those permissions having since expired.
If approved, the development would include about 1.7km of underground electrical cabling (33kV), a 38kV substation and an associated compound, including a 5.2-metre, single-storey control building with a floor area of 195 square metres.
The application also includes a new, upgraded site entrance and an access road. Almost 400m of underground electrical cabling (38kV) would run from the proposed substation to create a loop-in connection to the existing electricity network.
According to the planning documents, the proposed works would take place within or close to a European site or natural heritage area.
The concurrent application to Laois Co Council covers the elements of the development within the county’s administrative boundary.