Bagenalstown's new water treatment works are progressing well

he existing plant is currently working to the limits of its design
Bagenalstown's new water treatment works are progressing well

Uisce Éireann's upgrade works at Bagenalstown Wastewater Treatment Plant have now passed the halfway point

WORKS to upgrade the Bagenalstown Wastewater Treatment Plant have now passed the halfway point.

This significant investment by Uisce Éireann will more than double the current treatment capacity, increasing from a population equivalent of 4,500 to 9,800. It will also substantially improve the treatment processes at the existing wastewater treatment plant.

The existing plant is currently working to the limits of its design. This targeted investment by Uisce Éireann is required to ensure there is capacity available for future social and economic growth in the area, as well as ensuring compliance with national and EU legislation.

Significant progress has been made since works began last year, including the construction of inlet works, a new aeration tank and clarifiers alongside mechanical equipment installation, with all works due to be completed early next year.

“The works will be complete in early 2025, but the project will benefit Co Carlow for decades to come," said  Uisce Éireann’s portfolio manager Paul Fallon.

"When complete, the works will ensure compliance with wastewater treatment regulations and ensure adequate wastewater capacity for future growth. We would like to thank the local community for their support and co-operation as we carry out this work.” 

John Sisk & Son (Holdings) Ltd is carrying out the upgrade works on behalf of Uisce Éireann.

Uisce Éireann crews are also busy on the ground in Bagenalstown replacing almost 2.5km of aged and damaged water mains with new modern pipes in the town. These improvement works are a critical step in conserving water and reducing high levels of leakage. 

Works are progressing well, with more than 1.3km of the new pipes already installed. Full reinstatement, including roads and footpaths, have been completed along this stretch of 1.3km.

More in this section